• Kaniv HPP reconstruction continues

    In October 2016, within the framework of reconstruction of units 2 and 3 of Kaniv HPP (8 hydroelectric generating sets), Consortium "RPA "Ukrgidroenergobud" completed the dismantling of 110kV electrical components of the excitation system, control systems and auxiliary technological systems and cables.

    Construction work is carried out within the framework of reconstruction of buildings and facilities of Kaniv HPP.

  • Dniester PSPP received the certificate of conformity.

    In August 2016, the launch complex of the hydroelectric generating set 3 of Dniester PSPP, constructed by Consortium "RPA "Ukrgidroenergobud", got a compliance certificate issued by the State Architectural and Construction Inspectorate of Ukraine. The certificate confirms compliance of the complex with project documentation and its readiness for operation.

    The installed capacity of the third launch complex in the generating mode is 324 MW, in the pumping mode - 421 MW, which corresponds to the design data (by PJSC Ukrgidroproekt).

  • New equipment for Kaniv Hydroelectric Power Plant

    In March - May 2016, Consortium "RPA "Ukrgidroenergobud" supplied the following equipment to the Kaniv HPP:

    - generator electrical pathways of type MGC-DURESCA;

    - power equipment 110 kV;

    - power equipment 6,3 kV;

    - equipment of the drainage system and drainage of hydraulic units;

    - equipment of the industrial water supply system;

    - equipment for ventilation of premises ZRU-6.3 kV, above- and below- turbine premises of the hydroelectric generating sets of unit №3 and capsules of hydraulic units.