Dniester PSPP
Dniester PSPP
2018-2019 CONSTRUCTION OF THE SECOND STAGE OF THE DNIESTER PSPP
1
Dniester PSPP
Dniester PSPP
MAY 2017 - BEGINNING OF THE CONSTRUCTION OF THE SECOND STAGE OF DNIESTER PSPP
1
Dniester PSPP
Dniester PSPP
Year 2016. Continuation of the first stage of the Dniester PSPP
1
Dniester PSPP
Dniester PSPP
June 2016. Prime Minister of Ukraine V.Groysman on the construction of the Dniester PSPP
1
Dniester PSPP
Dniester PSPP
February 2016. The Stuff meeting for the construction of the Dniester PSPP
1
Dniester PSPP
Dniester PSPP
Year 2014. Continuation of work on the construction of the first stage of the Dniester PSPP
1
Dniester PSPP
Dniester PSPP
Year 2013. Construction and installation, start-up and adjustment operations
1
Dniester PSPP
Dniester PSPP
28-29 July 2014 - preparation for installation and erection of the scroll chamber of the hydrounit No. 3
1
Dniester PSPP
Dniester PSPP
October 24, 2014 - President of Ukraine Mr. Poroshenko Petro has visited Dnestr PSPP
1
Dniester PSPP
Dniester PSPP
December 18, 2014 - Signing of the Act of readiness for operation of the completed construction of the starting complex No. 2 of Dniester PSPP
1
Dniester PSPP
Dniester PSPP
16 May 2015 - Minister of Energy and Coal Industry of Ukraine visited the Dniester PSPP
1
Dniester PSPP
Dniester PSPP
May 15-16, 2015, July 3, 2015 - Delivery, unloading and installation of the runner of hydraulic unit No.3 in the crater of the hydrounit No. 3 shaft
1
Dniester PSPP
Dniester PSPP
September 6, 2014 - Start of hydraulic motor-generator No. 2 in the pump mode
2
Kaniv HPP
Kaniv HPP
2014-2016 year. Work on electrical equipment replacement in the reconstruction unit No.2 and No.3