News

  • INSTALLATION OF STATOR OF TURBINE OF UNIT №4 DNIESTER PSPP

    On December 11, 2018 stator of turbine with the elements of spiral case was mooved  from an erection site to the mine of hydroelectric generator №4. All pre-arranged building and installation works were executed in the mine of hydroelectric generator for providing move of stator of turbine weighing 287 tons.

  • THE NEXT STAGE OF CONSTRUCTION OF THE DNIESTER PSPP

    December 4, 2017 The second part of the elbow of the draft tube is loaded and placed in the design position into the mine of the 4th hydraulic unit. Specialists of the Consortium RPA Ukrgidroenergobud began the installation of two units in a complete 78-ton construction.

  • TRAINING IN ACCORDANCE WITH INTERNATIONAL STANDARDS ISO 9001: 2015 AND ISO 14001: 2015

    December 1, 2017. The specialists of the Consortium RPA Ukrgidroenergobud successfully completed the training course and received certificates under the program Training of Internal Auditors of the Quality Management System and Environmental Management of an enterprise, in accordance with international standards ISO 9001: 2015 and ISO 14001: 2015.

Pages