New equipment for Kanev hydroelectric station.
Published by admin on Wed, 01/04/2017 - 17:50
In March - May 2016, Consortium "RPA "Ukrgidroenergobud" supplied the following equipment to the Kaniv Hydro Power Plant:
- generator electrical pathways of type MGC-DURESCA;
- power equipment 110 kV;
- power equipment 6,3 kV;
- equipment of the drainage system and drainage of hydraulic units;
- equipment of the industrial water supply system;
- equipment for ventilation of premises ZRU-6.3 kV, above- and below- turbine premises of the hydroelectric generating sets of unit №3 and capsules of hydraulic units.
Equipment was delivered within the framework of reconstruction of units 2 and 3 of Kaniv HPP (8 hydroelectric generating sets).