April 16, 2018, Bureau Veritas Certification Ukraine conducted a supervisory audit in the Consortium RPA Ukrgidroenergobud, in accordance with the standards and norms of the International Organization for Standardization (ISO). The audit results confirmed the full compliance of the integrated quality and environmental management system, which operates in the Consortium, with the requirements of the international standards ISO 9001: 2015 “Quality Management Systems” and ISO 14001: 2015 “Environmental Management Systems”.
-
COMPLETING INSTALLATION OF METAL FACING OF VERTICAL CHANNEL
March 22, 2018
The Сonsortium RPA Ukrgidroenergobud, the general contractor for the construction of the Dniester PSPP, has loaded the last conduit #15 for the metal facing of the vertical supply channel No.4 into the mine shaft for installation. -
A meeting on the construction of the Dniester PSPP
February 8, 2018, representatives of the Consortium RPA Ukrgidroenergobud, a general contractor for the construction of the Dniester PSPP, took part in a meeting held at the branch of the Directorate for the construction of the Dniester PSPP, PJSC Ukrhydroenergo.
The main topics for discussion were uninterrupted provision of organizations involved in the construction of the second stage of the pump storage power plant (fourth unit), as well as optimization of production processes in order to comply with construction schedules.