  • New Project Consortium on Kaniv HPP

    Ukrgidroenergobud R&D Consortium jointly with OJSC Turboatom and SE Electrotyazhmash Plant will carry out some work upon results of the tender, conducted by OJSC Ukrgidroenergo, to supply 7 turbines, 7 generators, 8 sets of auxiliary systems to Kaniv HPS. They will perform dismantling, installing, commissioning work and put hydropower facilities into operation. 

  • Kanev HPP reconstruction continues

    In October 2016, within the framework of reconstruction of units 2 and 3 of Kaniv HPS (8 hydroelectric generating sets), Ukrgidroenergobud R&D Consortium completed the dismantling of 110kV electrical components of the excitation system, control systems and auxiliary technological systems and cables.

    Construction work is carried out within the framework of reconstruction of buildings and facilities of Kaniv HPS.

  • Dniester PSPP, received the certificate of conformity.

    In August 2016, the launch complex of the hydroelectric generating set №3 of Dniester PSPP, constructed by Consortium "RPA "Ukrgidroenergobud", got a compliance certificate issued by the State Architectural and Construction Inspectorate of Ukraine. The certificate confirms compliance of the complex with project documentation and its readiness for operation.

    The installed capacity of the third launch complex in the generating mode is 324 MW, in the pumping mode - 421 MW, which corresponds to the design data (by PJSC "Ukrhydroproject").