CONSTRUCTION OF THE DNIESTER PSPP - STAGES OF WORKS
May 25, 2018
The consortium RPA Ukrgidroenergobud has completed the next stage of work on reinforcing and preparing for concreting the construction of the gallery of technical water supply for hydraulic units No. 4 and No. 5 of the Dniester pumped storage power plant.
-
REPEARING OF WATER PIPES OF DNIPROVSKA HPP
In April 2018, the Consortium RPA Ukrgidroenergobud began repairing concrete surfaces and insulating the water pipes of the hydraulic units of the Dniprovska HPP branch of PJSC Ukrhydroenergo (Zaporizhia).
-
On April, 2018 the Сonsortium RPA Ukrgidroenergobud has installed the reinforced construction of the crane beam over the hydrogenerating unit No. 4 of the Dniester pumped storage power plant into the design position. The weight of the reinforced construction is 25.2 tons.